30th August
Another two
months on, and spring is already on our doorstep!
So here is
an updated on how the boats have been developing:
On
Number Three the frames have all been put in and glued in. The next
step was to reinforce the connection of the bulkhead and centrecase to
the frames and hull with Unis. After a round of peel ply and heat, the
hole was drilled for draining the front buoyancy tank, and the bung was
installed. However, we are not planning on cutting the inspection hatch
to open that bung unless the front ever takes on any water.
Next,
the foam for the false floor was cut based on the template, and
carboned on one side. Then we started fitting and re-shaping and
fitting and re-shaping it, until it sat quite nicely on the floor line
that was drawn on the side of the hull with a cedar batten.
One
of the trickier bits was to make the two parts forward and aft of the
bulkhead match. Furthermore, strips of foam were glued on the hull and
main bulkhead and centrecase to hold the false floor up. Final step was
cutting a hole in the transom and re-filling it with glue. This will
hold the bung to drain the aft buoyancy tank - but again, only after it
has taken on water for the first time.
So
it took quite a bit of preparation before the false floor could go
down. A bog-glue mix was applied to the underside (the one with carbon
on it) of the false floor where the frames are, and the two pieces were
fitted into the hull and weighted down with bricks and whatever else we
could find. The final touch was the wide cove around the outside
glueing the floor to the hull.
Final
preparation for putting carbon and glass on the false floor was to
router/dig out some spaces where the fibreglass reinforcements for the
mast step, the main sheet block and the mast support are going to go on
the floor. At one stage, the rounter changed its setting without
asking, which resulted into - some more glue needed that was not
originally planned for...
In
another major session, we carboned the inner side of the boat. To
prepare, the foam had to be sanded down and then bogged. After that,
the sheets of carbon were laid down one after the other and wetted out,
then the glass, which will be the sacrificial outer layer. After
putting down the peel ply, this step was vacuumed down to ensure an
nice finish and to squeeze out any excess resin.
Since then, some work has been done getting some foam
pieced together for the side decks. :

And here is the picture of Number Two; Grant has opted to cut the
Transom out before carboning down the false floor:
30th June
The month
has gone, and all three of us kept working on their respective boats.
In the
Winterless North, Number three has had the forward frames fitted:


An
intermission to take care of bubbles on the frames:

Then the
centrecase needed to be put together; hopefully square!

Coving the inside of the case:

Then the centrecase is in:

Unfortunately, this was the only batch of glue did not go
off, so we had to take it out again and glue it down once more.
Here's the next try:

The second hull now has all the frames neatly glued in:


The connection between the main bulkhead and the hull and
frames is reinforced with carbon unis:


Meanwhile,
the first hull was feeling the cold in Palmerston North and could not
be worked on until it is warm enough for the resin to react:

5th
to 7th June
Prime objective of this session was to get the first hull
to transportable stage, so the false floor had to go in.
For that, the mould had to be free, so
the third hull had to come out.

This time, popping the shell
out of the mould was a little harder again.

It
turned out there two somewhat palm-sized spots towards the port aft end
of the hull where the shell had stuck to the mould...

In
order to weigh down the floor uniformly, it was decided to put the
vacuum bag on it again as soon as the layers of carbon, glass and peel
ply were on it.
Therefore,
the mould was cleaned up and the first hull put into it again.
The
false floor was fitted, and reinforcements put into the floor for where
the mast post and the main sheet block were going to be placed.
False floor
in the boat (underside carboned):

The next
day, we tried to get the hull out of the mould again. It was sucked
down rather nicely.
Someone wondered what if it does not pop
out this time:

David, Antje
and Grant highly satisfied with their project this far:

Then the current status was
weighed:

Outer skin
only: 23kg
With frames
(not glued in): 30.5kg
With false
floor: 45kg
What the
decks will probably look like:

The first hull ready for transport to
Palmerston North:

29th May to
1st June
Wanting to
take advantage of the long weekend to do the long drive, David and Tony
Brown came up to the Bay of Islands
with the
trailer and new cradle to take the first hull back to Palmerston North.
Even
though quite a lot was achieved during those days, the first hull
was not yet ready at the end of the weekend,
and
the Browns had to leave the hull and trailer behind.
It must have
all happened quite quickly too, as there is no photographic evidence of
what went on during those four days.
The second
shell popped so easily out of the mould that Grant did that all by
himself on Friday afternoon.
To prepare
the mould for the third shell, it was again scraped, repaired, cut and
waxed.
Antje
insisted on the first film of glue to be left to go tacky before
putting the glass down.
This made
that first layer much harder to handle (maybe we should have rolled
some fresh resin in before laying the glass in).
There was a
little improvement of the final finish of the hull surface though, with
less of the glue left in the mould.
A real
improvement for the vacuuming was pre-bending the foam pieces for the
bow before starting the layup.
So
on the third hull the outer glass-carbon-foam layers went in within
four hours - at that rate we should keep on building those boats!
The
inner carbon layer also went down during that weekend, and David kept
putting in the under-floor reinforcements and false floor supports
whenever he
could be spared.
At this
stage we found out that we had under-estimated some of our material
use.
When David
was laying up the underside carbon layer for the first false floor,
there was no peel ply left.
Also, when
putting on the new vacuum bag, it was notices that instead of having
enough for six as planned,
the film was
only just enough to build a second one out of two pieces.
The great
satisfaction of the weekend was seeing the three hulls sitting neatly
in a row: So far so good!
1st and 2nd May
The big event: trying to release
the first shell from the mould! But first, to make sure the shell
was rigid when out, all frames were glued and coved in.
Coving the frames in while
in the mould:

And then: carefully removing the
shell from the mould:

Finally,
she is out:

But no rest
for the wicked, in goes the next one. Mould cleaned and repaired:

The next
outer skin was laid up (cove, glue rolled in, glass, carbon, foam) and
vacuumed down the next day.
25th April
Spontaneous
visit by Graham and David who happened to be 'around the corner' in
Auckland. Winds were too strong for racing the
18ft Skiffs, so what to do with half a Saturday?
Frames cut
out and ready for glueing

17th to 19th April
A busy weekend in the Bay of
Islands. A few photos below. Punching holes in the foam

Marking out the foam for cutting

Cutting the fibreglass for the
outside skin

Preparing the mould for the
outside layer of fibreglass

Carbon laminated in the mould

Putting the bog on the foam to
glue it to the carbon

Fitting the vacuum bag to the
mould

Checking for holes in the vacuum
bag

Making sure the vacuum pump
doesn't run out of oil

The foam after the vacuum bag was
removed

Making templates for the
underfloor frames

Putting the finishing
touches to the peelply on the inside skin of carbon

The clean-up crew hard at
work

April 6th
Here's our first progress report
on the boat building project in the
Far North: Both moulds have been repaired (and sanded and repaired and
sanded and repaired...) and cut with coarse and fine cutting compound.
Now comes the bit where we need some help: waxing the moulds. The foam
should be delivered today, and then we can also start laying up flat
panels with carbon for the frames. Grant and I will usually be at
Craig's workshop (Opua Industrial Estate) just after 5pm.
Come along to have a look!
 
See you...
Antje. |