Progress Timeline
Related Topics:
|
Current Progress
|
Virtual Javelin Index
|
Home
|
Progress Updates
To see earlier progress updates from the beginning of the project click the time period you are interested in.
Report Period
Description
Current Progress
Up to date progress on boat construction
7 July - 4 August 2000
Started to build the first hull on the mould. Hulls are being costructed over a male mould with the foam layers vacuum bagged down.
24 June - 6 July 2000
Completing the hull mould, and taking the first foredeck off the foredeck mould.
9 June - 22nd June 2000
Building the Hull Mould, attaching the plywood sheaving, glassing and fairing the Hull Mould.
24 May - 6 June 2000
Completing the hull building frame. Cutting hull frames with CNC machine, standing hull frames and attaching stringers.
1 May - 23 May 2000
Building the Foredeck and Sidedeck moulds. Initial work on the building frame.
13 April - 30 April 2000
Planning the project and machining down the mould stringers